Question: 1
A company is using Microsoft PPM to track task
progress. The company implements standard overtime
and non-billable time tracking.
You observe that you cannot enter overtime
hours in your current time sheet.
You need to ensure that you can enter overtime
hours. What should you do?
A. In your time sheet, add Overtime, and then
enter the overtime hours.
B. In your time sheet, switch to the My Work
view, and then enter the overtime hours.
C. In your time sheet, add Non-Billable, and
then enter the overtime hours.
D. Ask your project administrator to increase
Maximum Hours per Day.
E. In your time sheet, add the overtime hours to
your regular hours.
________________________________________________________________________
Question: 2
You
are a project manager using Microsoft PPM.
You need to create a new project that uses one of your
company’s templates.
What are two ways to achieve the goal? Each correct answer
presents a complete solution.
A. From Microsoft Project, select Enterprise.
B. In Project Center, select New, and then select the desired
enterprise project type.
C. In Resource Center, select New.
D. From Microsoft Project, select Featured.
___________________________________________________________________________________
Answers:
1 - Answer: A
2 - Answer: A,B
1 - Answer: A
2 - Answer: A,B